Keep up to date with 333 StK construction updates.

Please see below to view the latest news and construction updates for 333 StK.

AUG 2024

Completed preparation for Level 2 formwork. Forecasting to complete a new floor level every 3 weeks.

JUNE 2024

Basement Level 1 & concrete slabs are poured, works for Ground Floor commences.

333StK - May 2024 - Progress Updates
MAY 2024

Tower crane has been installed and Basement Level 2 concrete slab is poured and 80% complete. Formwork for Basement Level 1 is being prepared and ready for the concrete slab to be poured.

333StK - Mar 2024 - Progress Updates
MAR 2024

Basement excavation and shotcrete walls have been completed.

333 StK - Dec 23 - Commencement of Works
DEC 2023

Early works in progress.

DEC 2023

Initiation of earthworks by Balmain and Co.

333 StK - Dec 23 - Initiation of earthworks
NOV 2023

Matrix has selected the preferred builder, Balmain and Co., for the construction of 333 StK.

NOV 2023

Completing the design phase for 333 StK in collaboration with Rothelowman Architects at the display suite.