UPDATES
Keep up to date with 333 StK construction updates.
Please see below to view the latest news and construction updates for 333 StK.
APRIL 2025
Internal fit-out works nearing completion in 333 StK. Building is still on schedule to be completed by the next quarter of the year.
MARCH 2025
Internal fit-out works are progressing smoothly for the building. 333 StK is well on track to be move-in ready by Q3 2025.Â
DEC 2024
Building structure is 100% complete. Construction progress is over 50% with internal fitout works as well as window and façade installation currently underway.
OCT 2024
Construction of 333 StK progressing quickly with 5th floor concrete slab poured. Stunning views of surrounding St Kilda from this level.
AUG 2024
Completed preparation for Level 2 formwork. Forecasting to complete a new floor level every 3 weeks.
MAY 2024
Tower crane has been installed and Basement Level 2 concrete slab is poured and 80% complete. Formwork for Basement Level 1 is being prepared and ready for the concrete slab to be poured.
DEC 2023
Matrix has selected the preferred builder, Balmain and Co., for the construction of 333 StK.
NOV 2023
Completing the design phase for 333 StK in collaboration with Rothelowman Architects at the display suite.